1. Introduction

Oracle released Primavera P6 Version 20 PPM for download from their web site late in 2020.

Oracle released a document that outlines all the changes from Version 19 to P6 Version 20 in a document titled Oracle Primavera P6 Cumulative Feature Overview P6 Professional 19.12 20.11 Release Feature Overview.

Oracle Primavera also has two Cumulative Feature Overview (CFO) tools for tracking changes in the P6 EPPM and PPM versions:

2. Aim

The aim of this document is to expand on the document published by Oracle and outline the changes a PPM user will see in the software and add some comments on the usability of the features including:

  • New login screen
  • User Defined Fields Details tab Relationship Comments
  • Relationship Comments
  • Role Rate Change Over Time
  • Multiple Project Scheduling Data Date Selection
  • Multiple Project Scheduling Options Selection
  • Lean Tasks may be imported using an XML file
  • Different Projects may have different Financial periods
  • Assignment CodesHistogram Bars Exact Values
  • Histogram Bars Exact Values
  • Other Enhancements
    • Resource Assignment Window now allows Grouping and Filtering by Codes and UDFs
    • Fill down available in Activities Window Resource Usage Spreadsheet
    • P6 Continues Working when there is a Network Failure
    • Prevent Risk Categories being Imported into a PPM Database
    • Arabic Language
    • Reset Locked Users
    • Uploading of Harmful Files
    • Exception Site List
Oracle Primavera P6 Delay Analysis Techniques

3. New login screens

P6 Version 20 has introduced new login screens:

These have the same information but just a different format.

4. User Defined Fields Details tab

This function was introduced in Version 19 but so useful I have added it to this article. A User Defined Field Details tab is now available in many workspaces such as Projects, Resources, Activities and WBS:

This is extremely useful as it allows users to see and assign UDFs without having to add extra columns to their Layouts.

5. Relationship Comments

A Comments column may be added to the Activities window Relationships, Predecessor and Successor tabs:

The comment is seen in both the Predecessor and Successor window of each relationship assigned a comment:

This is a very useful function and in the past one had to either use a Note or a UDF assigned to either the predecessor or successor activity to record notes about a relationship.

This function is also useful for recording changes to relationships.

The Comments column is available in the Activity Relationship report:

6. Role Rate Change Over Time

Resources have always been able to vary their rate over time but Roles were not and this was one of the drivers to use resources and not roles on projects.

When an activity spans two periods then P6 calculates a proportional rate based on the activity duration in each period. You must use the Recalculate Cost Assignment function during or after rescheduling.

The pictures below show the result of assigning the Role Foreman above and has 4 days work in 2020 and 6 in 2021 and then 3 and 7 days. They demonstrate how the cost are calculated which are not entirely correct as the costs should be lower in 2021 and higher in 2022.

Note: This is the same way that resources calculate when an Activity spans an Effective Date.

7. Data Date Selection in Multiple Project Scheduling

When scheduling multiple projects you now have a choice of the Data Date used for calculating:

  • All projects may be assigned a new Data Date in the Schedule form, or
  • New in P6 Version 20, you may schedule all projects with their own Data Date.

8. Multiple Project Scheduling Options Selection

In the P6 Version 19 and earlier when multiple projects were scheduled together and they had different Scheduling Options, which could happen when users change them from default or when you imported a project, then all the different Scheduling Options of all the projects being scheduled were changed to the Default Project on a permanent basis and changed projects would calculate differently from then on.

The Default Project may still be set by selecting Project, Set Default Project:

But now you may select which project Scheduling Options are used when scheduling multiple project in the Scheduling Options form which is opened by selecting Tools, Schedule, Options:

What happens now?

  • The Default Project is ignored,
  • The Scheduling Options from the project selected in the Scheduling Options are used to calculate all the project, and
  • The other project(s) Scheduling Options are changed permanently to the project selected the Scheduling Options form on a permanent basis.

Thus, the problem of Scheduling Options being changed when scheduling multiple projects has NOT been solved. You now have two options to mess up your Scheduling Options of projects when scheduling multiple projects with different options.

Again, I reiterate you should make all the Scheduling Options in one database the same when you schedule multiple projects and be careful when importing projects.

9. Lean Tasks may be imported using an XML file

Primavera Cloud allows activities to be broken down into tasks.Lean Tasks are similar to the P6 Steps function but with more functionality such as allowing the assignment of tasks to subcontractors. Lean Tasks may have the following attributes:

  • Assignment of a duration,
  • May be made “Private” so other people do not see them,
  • Tasks may have logic between them which are called “Handoffs”,
  • A Task’s Float is called “Slack”.
  • The planning of Tasks is completed on a Planning Board that may be shared between team members. This is a tool designed for short term planning by the people completing the work.

When you are using an EEPM database you may Import Lean Tasks through an XML file from Primavera Cloud.

10. Different Projects may have different Financial periods

You may now assign different Financial Period to projects in P6 Version 20 by the use of Financial Period Calendars. When you select Admin, Financial Period Calendars you may create multiple Financial Period Calendars and each may have different Financial Periods:

The Financial Period Calendars is assigned to a Project in:

  • The Projects Window, General tab, or
  • By displaying the Financial Period Calendar column:

Note: This function did not work in the authors P6 Version 20.12.0.37740, but updates should fix this issue. As an interim you may change the Default Financial Period Calendar before creating a project.

11. Assignment Codes

There is a new function titled Assignment Codes allowing users to code up assignments so resource assignments may be Grouped or Filtered. This function could be used for:

  • Assigning priority to resource assignments against tasks,
  • When there is one generic resource in the database that is being supplied by multiple subcontractors and this could be used to identify the subcontractor,
  • When there is one generic resource in the database and you require a specific skill or qualification for the resource then this could be identified with an Assignment Code.

Assignment Code. are created in the same way as other codes by selecting Enterprise, Assignment Code:

Assignment Code. are assigned to Resource or Role Assignments in the:

  • Codes tab in the Resource Assignment window, or
  • Displaying the Assignment Code column in the Activities window Details pane, Resourcestab, or

  • Displaying the Assignment Code column in center section of the Resource Usage Spreadsheet.

12. Histogram Bars Exact Values

In P6 Version 20 value of histograms may be displayed on histograms in the Resource Usage Profile, Activity Usage Profile, and Tracking View by selecting the Show Values option in the Profile Option form, Graph tab:

13. Other Enhancements

13.1 Resource Assignment Window now allows Grouping and Filtering by Codes and UDFs

Data in the Resource Assignment window may be filtered and/or grouped using Project, Activity and WBS User Defined Fields (UDFs) and Project Codes in P6 Version 20.

13.2 Fill down available in Activities Window Resource Usage Spreadsheet

Fill down is available in the Activities Window Resource Usage Spreadsheet in P6 Version 20.

13.3 P6 Continues Working when there is a Network Failure

Users may continue working is some circumstances when connected to an EPPM Cloud Connect database and configured to allow this when there is a network failure.

13.4 Prevent Risk Categories being Imported into a PPM Database

When exporting to an XER file Risk Categories are exported but in P6 Version 20 you are able to prevent the Categories being imported into a PPM or SQLite database.

13.2 Fill down available in Activities Window Resource Usage Spreadsheet

Fill down is available in the Activities Window Resource Usage Spreadsheet in P6 Version 20.

Risk Categories are not imported or exported to an EEPM database.

13.5 Arabic Language

Arabic is supported in P6 Version 20.

13.6 Reset Locked Users

In the EPPM version users locked out of P6 or Visualizer may be reset.

13.7 Uploading of Harmful Files

You may prevent people from uploading harmful files in the Admin Preferences, Options, Document Security:

13.8 Exception Site List

A list of web sites may be added to Admin Preferences, Options, Exception Site List:

The URLs may then be added to Notebook Topics and UDFs and permitted URLs may be launched from P6 by clicking on the URL and selecting Launch.

URLs not listed or not permitted may not be launched but may be copied and pasted into a browser. The picture below demonstrates what happens when a URL that has not been enabled has been selected for Launching:


Paul E Harris
Director Eastwood Harris Pty Ltd
14 January 2021
www.eh.com.au

View original content source